Industrial engineering calculator

Machine Requirement Calculator

Calculate the number of machines needed for each operation and by machine type from an operation breakdown, daily target, working hours and planned efficiency.

Inputs

Operation breakdown
pcs
h
%

Result

Machines required

18machines

Overlock 4T
11machines
Flatlock
6machines
Single needle lock
1machines
Theoretical total (unrounded)
15.25
Working
  1. Total SMV = 4.27 min
  2. Minutes available per machine = 480 × 70% = 336
  3. Shoulder join: 1,200 × SMV / 336 = 1.25 -> 2
  4. Neck rib join: 1,200 × SMV / 336 = 1.79 -> 2
  5. Neck top stitch: 1,200 × SMV / 336 = 1.5 -> 2
Machines by operation
OperationMachineExactAllocated
Shoulder joinOverlock 4T1.252
Neck rib joinOverlock 4T1.792
Neck top stitchFlatlock1.52
Sleeve attachOverlock 4T2.863
Side seamOverlock 4T3.214
Sleeve hemFlatlock1.962
Bottom hemFlatlock1.792
Label attachSingle needle lock0.891

Formula

Formula
Nop=Q×SMVopT×ηN_{op} = \dfrac{Q \times \text{SMV}_{op}}{T \times \eta}

Machines for an operation = daily target × operation SMV / (working minutes × efficiency)

SymbolMeaningUnit
QDaily targetpcs
SMV_opOperation SMVmin
TWorking minutes per daymin
ηPlanned efficiency as a fraction-

How the calculator works#

Minutes available per machine = working minutes × planned efficiency. For each operation, machines = daily target × operation SMV / minutes available per machine. Each operation is rounded up, then totals are grouped by machine type.

Worked example#

Defaults: a T-shirt with eight operations (total SMV 4.27), target 1,200 per day, 8 hours, 70% efficiency.

  • Minutes per machine = 480 × 0.70 = 336
  • Side seam (SMV 0.90): 1,200 × 0.90 / 336 = 3.21, rounded up to 4
  • Sleeve attach (SMV 0.80): 2.86, rounded up to 3
  • Theoretical total = 15.25 machines; rounded total = 18 machines: 11 overlock, 6 flatlock, 1 lockstitch

Interpreting the result#

The gap between 15.25 and 18 shows the cost of rounding each operation separately. Look for operations on the same machine type that one operator can combine, such as shoulder join and neck rib join. Then confirm the layout with line balancing.

Assumptions

  • Each operation gets whole machines, rounded up. Combining small operations on one machine is a line balancing decision made afterwards.
  • Machine type names must match exactly to be grouped.

Common errors

  • Rounding the line total instead of each operation, which under-provides machines.
  • Forgetting spare machines for breakdowns and style changeover.

Questions

Why is each operation rounded up?

An operation that needs 1.25 machines in theory needs two machines unless it can share a machine with another operation. Review the rounded result and combine operations where the machine type and layout allow.

Should I add spare machines?

Many factories keep a small number of spares for breakdowns and style changes. Add them after the calculation.