Garment Line Efficiency: Formula, Example and Calculator

Line efficiency compares the minutes a sewing line earned with the minutes it had. Learn the formula, work through examples, understand what drives efficiency up and down, and avoid the reporting mistakes that make the number meaningless.

By Published 4 min read
On this page

Line efficiency tells you how much of the time a sewing line had was turned into standard work. It is the most watched number in garment production, and one of the most misused.

The formula#

Efficiency=Output×SMVManpower×Working minutes×100\text{Efficiency} = \frac{\text{Output} \times \text{SMV}}{\text{Manpower} \times \text{Working minutes}} \times 100
  • Output is good garments completed in the period.
  • SMV is the standard minute value of the garment.
  • Manpower is the number of people counted in the line.
  • Working minutes is the time each person was available in the period.

The top of the fraction is earned minutes: the standard time for the work done. The bottom is available minutes: the time paid for. Efficiency is the ratio.

Worked example#

A T-shirt line has 40 people and works 8 hours (480 minutes). The garment SMV is 12.0. At the end of the day, 1,000 good T-shirts have passed end-of-line checking.

  • Earned minutes = 1,000 × 12.0 = 12,000
  • Available minutes = 40 × 480 = 19,200
  • Efficiency = 12,000 / 19,200 × 100 = 62.5%

Try your own numbers in the line efficiency calculator.

What efficiency really measures#

Efficiency above 100% means the line earned more standard minutes than it had. That can be genuine on a mature style with skilled operators, but it more often means the SMV is too loose, output was over-counted or manpower was under-counted.

Efficiency well below plan means time was lost somewhere. The loss usually comes from a combination of:

Source of loss Examples
Balancing Operators waiting for work behind a bottleneck
Method Poor workplace layout, missing attachments, extra handling
Skill New operators, operators on unfamiliar operations
Machines Breakdowns, wrong settings, needle and thread problems
Material Late cut panels, missing trims, shade or measurement problems
Quality Time spent on repairs instead of new work
Style changes Learning curve after a changeover

The low line efficiency troubleshooting guide works through these in order.

Off-standard time#

Some lost minutes are outside the line's control: a power cut, waiting for cut panels, a machine waiting for a mechanic. Many factories record these minutes as off-standard time and calculate two numbers:

On-standard efficiency=Earned minutesAvailable minutes−Off-standard minutes×100\text{On-standard efficiency} = \frac{\text{Earned minutes}}{\text{Available minutes} - \text{Off-standard minutes}} \times 100

On-standard efficiency shows how well the line worked when it could work. Overall efficiency shows the business result. Both are useful; report which one you are using.

Who counts as manpower#

This is the most common source of disagreement. Decide once, write it in your procedure, and keep it:

  • Operators only gives a higher number, useful for comparing operator performance.
  • Operators and helpers reflects the direct labour cost of the line.
  • All line staff, including supervisors, line quality checkers and ironmen, reflects the full cost.

A line's efficiency can move by ten points just from a change in who is counted. That tells you nothing about how the line worked.

Efficiency and targets#

Target and efficiency are the same equation rearranged:

Target=Manpower×Minutes×EfficiencySMV\text{Target} = \frac{\text{Manpower} \times \text{Minutes} \times \text{Efficiency}}{\text{SMV}}

A line planned at 65% with 40 people, 480 minutes and SMV 12 has a daily target of 1,040 pieces. If it makes 1,000, it ran at 62.5%. See production target calculation.

Improving efficiency#

Work on causes, not on the number:

  1. Balance the line so no operator waits and none is overloaded. See line balancing and bottleneck analysis.
  2. Fix the method at the slowest operations: workplace layout, attachments, folders, pick-up and aside positions.
  3. Keep machines ready: correct needles, tension, SPI and preventive maintenance.
  4. Secure material flow from cutting so the line never waits for input.
  5. Build quality in with inline checks, so time is not lost on repairs.
  6. Plan for the learning curve when styles change.

Common reporting mistakes#

  • Counting repaired or unchecked garments as output.
  • Using a costing SMV that is different from the SMV the line is working to.
  • Mixing overtime minutes in or out between days.
  • Changing the manpower definition between lines or reports.
  • Comparing efficiency between factories without checking SMV method and scope.
  • Operator efficiency applies the same idea to one person and one operation.
  • Pieces per operator per day is simpler but meaningless across different styles.
  • OEE is used for machine-paced processes. See OEE in garment manufacturing.

The capacity calculator uses average efficiency to plan how much a factory can book.